Valves
are the most common equipment in chemical enterprises. Installing valves may
seem easy, but if not carried out according to relevant technical standards, it
can lead to safety accidents. Today, we would like to share some experience and
knowledge about valve installation with you.
I. Conduct a water pressure test during winter
construction at negative temperatures.
-
Consequence: Due to
the rapid freezing inside the pipe during the hydrostatic test, the pipe is
damaged by freezing.
-
Measures: Try
to conduct a water pressure test before winter construction, and blow out the
water after the test, especially the water inside the valve must be completely
removed, otherwise the valve may rust or even freeze and crack. When conducting
a water pressure test in winter, the project must be carried out at a positive
temperature indoors, and the water must be blown out after the test.
II. The pipeline system is not washed carefully before
completion, and the flow and speed cannot meet the requirements of pipeline flushing.
-
Consequences: Water
quality cannot meet the operational requirements of the pipeline system, often
resulting in reduced pipeline cross-sections or blockages.
-
Measures: flushing
should be carried out with the maximum design flow rate in the system or a
water flow rate of not less than 3m/s. It should be considered as qualified if
the water color and transparency at the outlet are visually consistent with
those at the inlet.
III. Sewage, rainwater, and condenser pipes are
concealed without undergoing a closed water test.
-
Consequences: It
may cause water leakage and cause losses to users.
-
Measures: The
closed water test work should be strictly inspected and accepted according to
the specifications. The concealed installation of sewage, rainwater, condenser
pipes, etc. in underground burial, ceiling, and between pipes should ensure no
leakage.
IV During the hydraulic pressure strength test and
tightness test of the pipeline system, the leakage inspection is not
sufficient.
-
Consequence: Leakage
occurs after the pipeline system is running, affecting normal use.
-
Measures: When
testing the pipeline system according to design requirements and construction
specifications, in addition to recording pressure values or water level changes
within the specified time, it is particularly important to carefully check for
leakage problems.
V. The flange plate of the butterfly valve is made of
ordinary valve flange plate.
-
Consequences: The
dimensions of the flange plates for butterfly valves and ordinary valves are
different. Some flanges have a small inner diameter, while the butterfly
valve's disc is large, causing it to be unable to open or to open forcibly,
resulting in damage to the valve.
-
Measures: The
flange plate should be processed according to the actual size of the butterfly
valve flange.
VI. The valve installation method is incorrect.
For
example, the water (steam) flow direction of the stop valve or check valve is
opposite to the mark, the valve stem is installed downward, the horizontally
installed check valve is installed vertically, the handle of the open-stem gate
valve or butterfly valve has no space for opening and closing, and the valve
stem of the concealed valve does not face the inspection door.
-
Consequences: Valve
malfunction, difficulty in switch maintenance, and often water leakage caused
by the valve stem pointing downwards.
-
Measures: Install
the valve strictly according to the installation instructions. For the rising
stem gate valve, leave enough space for the valve stem to extend and open. For
the butterfly valve, fully consider the space for rotating the handle. The
valve stem should not be lower than the horizontal position, and it should not
be downward. For concealed valves, not only should there be an inspection door
that meets the needs of opening and closing the valve, but also the valve stem
should face the inspection door.
VII. The specifications and models
of the installed valves do not meet the design requirements.
For
example, the nominal pressure of the valve is less than the system test
pressure; gate valves are used for water supply branch pipes with diameters
less than or equal to 50mm; stop valves are used for hot water heating dry and
vertical pipes; and butterfly valves are used for fire pump suction pipes.
-
Consequences: It
affects the normal opening and closing of the valve and the adjustment of
resistance and pressure. It may even cause damage to the valve during system
operation and necessitate repairs.
-
Measures: Familiarize
yourself with the application scope of various valves, and select the
specifications and models of valves according to the design requirements. The
nominal pressure of the valve should meet the requirements of the system test
pressure. According to the construction specifications, when the diameter of
the water supply branch pipe is less than or equal to 50mm, a globe valve
should be used; when the diameter is greater than 50mm, a gate valve should be
used. The hot water heating dry and riser pipes should use gate valves, and the
suction pipe of the fire pump should not use butterfly valves.
VIII. The necessary quality inspection is not
conducted according to the regulations before the installation of the valve.
-
Consequences: The
valve switch is not flexible during system operation, resulting in poor closure
and leakage (steam) phenomena, causing rework and repair, and even affecting
normal water (steam) supply.
-
Measures: Before
the installation of valves, pressure strength and tightness tests should be
conducted. The tests should be conducted on 10% of each batch (of the same
brand, same specification, and same model) and no less than one. For
closed-circuit valves installed on the main pipe to cut off, strength and
tightness tests should be conducted one by one. The pressure for valve strength
and tightness tests should comply with the provisions of the Code for
Acceptance of Construction Quality of Water Supply Drainage and Heating Works
(GB 50242-2002).
IX. Improper installation of valves in high
temperature environment.
-
Consequence: leakage
accident
-
Measures: For
high temperature valves over 200℃, they are at normal temperature during
installation, but after normal use, the temperature rises, the bolts expand due
to heating, and the gap increases, so they must be tightened again, which is called
"hot tightening". Operators should pay attention to this work,
otherwise leakage is likely to occur.
X. Valve flip-chip
-
Consequences: Valves
such as stop valves, throttle valves, pressure reducing valves, and check
valves all have directionality. If installed upside down, the throttle valve
will affect the effectiveness and lifespan of the valve; the pressure reducing
valve will not work at all, and the check valve may even pose a danger.
-
Measures: General
valves have directional signs on the valve body; if not, they should be
correctly identified based on the working principle of the valve. The valve
cavity of the globe valve is asymmetric left and right, and the fluid should be
allowed to pass through the valve port from bottom to top, which reduces fluid
resistance (determined by shape) and saves effort when opening (due to the
upward pressure of the medium). After closing, the medium does not press on the
packing, which is convenient for maintenance. This is why the globe valve
cannot be installed backwards. Gate valves should not be installed upside down
(i.e., with the handwheel facing down), otherwise the medium will remain in the
valve cover space for a long time, which can easily corrode the valve stem and
is also prohibited for certain process requirements. At the same time, it is
extremely inconvenient to replace the packing. For rising stem gate valves, do
not install them underground, otherwise the exposed valve stem will be corroded
due to moisture. For lift check valves, ensure that their valve discs are
vertical during installation to facilitate flexible lifting. For swing check
valves, ensure that their pin shafts are horizontal during installation to
facilitate flexible swinging. Pressure reducing valves should be installed
upright on horizontal pipelines, and should not be tilted in any direction.